top of page
Top
IMG_1148.JPG
ocean-county-seal-2019.png

Chadwick Beach Island Bridge

(Strickland Blvd) Over Barnegat Bay

Virtual Public Information Meeting
#4

Purpose & Need
Purpose & Need
  1. Restore the structural, geometric, and operational integrity of the bridge in compliance with current design standards

  2. Provide a safe, efficient, and reliable crossing for all modes of transportation.

timeline

Concept Development Complete

August 2018 thru June 2020

Identifies and compares reasonable alternatives and strategies that address the purpose and need statement and selects a preliminary preferred alternative (PPA). Once a concept development report is completed, the Interagency Review Committee (IRC) will determine whether or not the project can be advanced to the next phase.

 

Preliminary Engineering

May 2022 thru November 2023

Project will be further developed and refined to a level of detail necessary to secure the approval of the environmental document, also known as the NEPA (National Environmental Policy Act) document. Once the project obtains NEPA approval and is accepted by the IRC, the project advances to the next phase.  (Currently underway.)

 

Final Design

Estimated Spring 2024 thru Fall 2025

This phase will produce construction contract documents (i.e., Final Plans, Specifications, and Cost Estimates (PS&E)), and if necessary, acquire right-of-way. Once the PS&E package is approved by NJDOT and authorized for construction by FHWA, the project is eligible to advance to the final phase.

 

Construction

Estimated Spring 2026 thru Summer 2028.  

The project will be advertised, awarded, construction management systems and processes will be established, and construction will commence. The project is considered completed, when the final phase is closed out with NJDOT and FHWA.

goals
Timeline
Goals & Objectives
  1. Maintain island access to the greatest extent practical and minimize impacts to residents by optimizing the construction duration.

  2. Avoid or minimize impacts to vehicular and marine traffic, pedestrians and bicyclists during construction.

  3. Maintain existing clearance.

  4. Avoid or minimize social, economic and environmental impacts.

  5. Enhance bicycle and pedestrian compatibility in this recreational community.

  6. Consider the context of the project area and identify aesthetic enhancements.

summr
Construction

The project team has made it a point to limit impacts during the Summer recreational season. Work will only be done during the off-season. Click the link below to see how construction will be staged.

​

07142022 Progress Mtg 3-span Alt v2_Page_09.jpg
contact
IMG_1117.JPG

Comments/
responses

Thank you for leaving a comment during the PIC period. Submitted comments and responses are now available.

bottom of page